Current Project Responsibilities and Deadlines:

  • Finish drafting Operations & Maintenance manual: drawings, operation & maintenance procedures, troubleshooting, equipment log sheets, safety procedures, spare parts lists
  • Compile a project history on tingopucaradevelopment.wordpress.com
Project meetings are currently happening on Tuesday nights at 7:00 pm. If you would like to help, please contact us.
Comments Off

Update from George

George Beane sent us an update on the storage tank construction and the electrical line status today. The main tank structure has been completed and is looking great.

Many of the supplies for the pipeline were recently delivered. The community received 120 incorrect stainless steel unions from the supplier, but the supplier has agreed that it was a mistake and will be delivering the correct unions soon.

We are still waiting for the electrical utility company to run electricity to the pump house, but George has made contact with the company, and this work will be started soon.